Mumbai-Ahmedabad Bullet Train: Surat station takes shape, BKC station work underway; check launch update
Reported by ET Now
Mumbai-Ahmedabad Bullet Train: The Mumbai-Ahmedabad Bullet Train project is moving closer to its planned launch in August 2027, with construction work progressing across key sections of the 508-km high-speed rail corridor. Fresh updates show significant progress at the Surat station in Gujarat, while foundation work is underway at the Bandra-Kurla Complex (BKC) station in Mumbai.
The project, being implemented by the National High-Speed Rail Corporation Limited (NHSRCL), will connect Mumbai with Ahmedabad through a high-speed rail corridor covering Maharashtra, Gujarat and the Union Territory of Dadra and Nagar Haveli. Surat station gets diamond-inspired design The Surat bullet train station is taking shape with a de
According to the latest project update, the main structural work at the Surat station has been completed, while interior and finishing work is now underway. The station is among the major stations being developed along the corridor. The Mumbai-Ahmedabad corridor will have 12 stations in total, connecting several important cities and industrial centres along the route.
BKC station construction progresses At Mumbai’s Bandra-Kurla Complex, construction work on the underground bullet train station is progressing. The BKC station forms an important part of the Mumbai section of the project, which includes major underground construction.