India's First Bullet Train Moves Closer As 50-Km Surat-Bilimora Section Gets Power Supply

Reported by Republic World

New Delhi: The Overhead Equipment (OHE) system on the Surat–Bilimora section of the Mumbai–Ahmedabad Bullet Train corridor received energisation on November 20. This development covers both the Up and Down lines along the elevated alignment, moving the first Bullet Train project in India closer to further testing activities.

The energised stretch spans approximately 50 kilometres between the Surat and Bilimora stations. The corridor utilises a 2 x 25 kV Overhead Traction System, an electrification technology deployed on high-speed rail networks globally. Along the 508-kilometre corridor, the electrification network includes 14 Traction Substations (TSS) that draw power from the National grid to feed the overhead traction system for the trains.

At Bilimora, located in the Navsari district of Gujarat, the first Traction Substation completed installation works across its Control Panel, Changeover Switch, Transformer, and Circuit Breaker buildings. This Gujarat substation sources its power from the 220 kV Ambetha Grid Substation operated by Gujarat Energy Transmission Corporation Limited (GETCO).

A centralised control centre will monitor the entire electrical network to maintain operational safety and reliability. The 50-kilometre elevated alignment between Surat and Bilimora features bridges spanning four rivers alongside a steel bridge constructed over National Highway 53 (NH-53).