Why a Mumbai Metro line is waiting for one man in a crumbling building to move
Reported by The Indian Express
At Juhu Circle, one of the busiest junctions in Mumbai’s western suburbs, two crumbling apartment blocks stand almost empty. The residents moved out over the years as the buildings grew dangerous. One man remains. In his mid-fifties, he has lived here since childhood.
The building he calls home is the last thing standing in the way of a Metro line. Mumbai is building Metro Line 2B, a 23.643-kilometre elevated corridor across its suburbs at a cost of Rs 10,986 crore. On the 8-kilometre stretch due to open next — between Andheri and Khar, the tracks are laid on every inch, except 185 metres.
That missing piece of the elevated track has to pass over the plot where the man lives. It has taken eight years, a High Court case and two failed deals to clear those 185 metres. Until they are built, trains can’t run. The gap sits between DN Nagar and ESIC Nagar stations, at the point where the new line joins the operational Line 2A, so there is no way around it.
Because of the gap, tracks cannot be laid along the full stretch. Until that is done, the MMRDA cannot put up the overhead electric poles, power the line or begin trial runs. The stretch has been held up for at least eight months, and commuters in Vile Parle, Santacruz and Khar are still waiting for the Metro to reach them.