Parel terminus plan will take 7 years to execute: Officials
Reported by Mumbai Mirror
Internal letter highlights difficulties in land acquisition.
The railways’ plan to construct an outstation train terminus at Parel station has run into difficulties, with Central Railway officials admitting that the project may take six to seven years to complete. An internal letter signed by the chief traffic planning manager, Mani Jit Singh, chief engineer, Mumbai Traffic Project, SS Kedia, and chief mechanical engineer, Planning, SK Jain, accessed by Mumbai Mirror, says acquiring land for the project will not be easy.
The admission comes even as worker unions continue to oppose the project, saying there is no need to build an outstation terminus at Parel.
There is a requirement of 6,320 square metres of land of the National Textile Corporation (NTC) for providing necks for the coaching complex at the Dader end of the proposed project, the letter says. “This acquisition could be difficult since a piece of 2,656 square metre earlier asked from the NTC for the fifth and sixth [track] line (adjacent to the plot) has not been agreed to as yet by them [the Ministry of Textile] despite following up at the highest levels.”
That is not all. The letter adds that at the Currey Road end, 1,927 square metres of private land is also required during Phase 2 for an engine reversal facility.