Mumbai Water Metro Moves Ahead With ₹1,621-Crore Phase 1
Reported by Urban Acres
Mumbai’s Water Metro project has moved closer to implementation after the Maharashtra Maritime Board (MMB) selected a joint venture of TYPSA India Pvt. Ltd. and RINA Consulting SpA as the Project Management Consultant for Phase 1, according to Maharashtra minister Nitesh Rane.
The appointment and the proposed consultancy expenditure of ₹31.98 crore still require approval from the state government. The MMB approved submitting a proposal seeking administrative approval for the fee at its 89th board meeting.
The consultant will review the Detailed Project Report prepared by Kochi Metro Rail Limited and support planning, design and procurement. It will also supervise the construction of passenger terminals and related infrastructure, the report said.
Phase 1 has an estimated civil infrastructure cost of ₹1,621 crore and is targeted for completion by 2029. The plan covers 16 routes—eight existing and eight proposed—and the development or upgrading of 26 passenger terminals.
Three terminals at the Gateway of India, Navi Mumbai International Airport and Nariman Point are being implemented by other agencies and are outside the core infrastructure scope. The project management consultant is expected to coordinate with those agencies to support network integration.