Mumbai Metro Line 5 First Train Reaches Kasheli Depot

Reported by constructionworld.in

The delivery will enable MMRDA to undertake initial inspections and other depot-related preparations while work continues on the remaining infrastructure. Kasheli Depot will serve as the principal facility for parking, testing, inspection and maintenance of trains operating on the corridor.

The depot is spread across 27 hectares and is being developed to accommodate around 30 trainsets. Basic facilities completed for receiving the first train include a coach loading and unloading platform and a temporary inspection bay. The planned infrastructure includes five inspection lines, four workshop lines, a dedicated test track and train-washing facilities.

Preparations for corridor testing began before the dedicated train arrived at Kasheli. Electrification work on Line 5 was completed in September, while a trainset kept at Mandale Depot was transported coach by coach to the Line 4 corridor in Thane. It was subsequently moved to Line 5 through the interchange connection at Kasarvadavali during Navratri to support the start of trial runs.

Read the full report at constructionworld.in