Mumbai Metro 2B inches closer to completion as MMRDA races to install the final three girders at Juhu Circle, bringing the 7.53-km Andheri West-Saraswat Nagar stretch closer to its March 2027 deadline; with 75% of work completed
Reported by The Times of India
The final phase of construction on the Andheri-Bandra stretch of Metro Line 2B is nearing completion, with MMRDA targeting the installation of the last three girders near ESIC Metro Station at Juhu Circle by November 18.
The 7.53-km Andheri West-Saraswat Nagar stretch is targeted to open by March 31, 2027. However, the opening may be delayed until the monsoon due to pending construction work.
Metro Line 2B has achieved 75% progress in civil and systems works. Construction activities include the installation of the remaining girders near ESIC Metro Station at Juhu Circle.
At Juhu Circle, 20 precast prestressed concrete I-girders are being installed across five spans, covering 150 metres between Metro piers EC29 and EC35. Civil construction on this stretch is being carried out by J Kumar Infraprojects.
The girders being installed near Juhu Circle measure 33 metres in length and 1.22 metres by 2.25 metres in cross-section, with each weighing 115 metric tonnes. Of the total 20 girders, 17 have already been erected, while three remain pending.