CONCRETISATION PROJECT: City roads to remain dug up till 2030
Reported by Mumbai Mirror
The BMC has invited tenders worth Rs 8,614 crore for the third phase of its road concretisation project, covering 1,437 roads spanning 452 kilometres across Mumbai. The civic body plans to begin work in October 2027, after completing the first two phases in January 2027, with the entire project targeted for completion by December 2030.
The third phase will involve full-width concretisation of 1,261 roads covering 313 km, along with completing pending side-strip work on 176 roads spanning 139 km. The project will also include upgrading key road junctions and connecting stretches to ensure smoother vehicular movement.
Although the bidding process is currently underway, actual excavation and construction will begin only after the ongoing first two phases are completed. The BMC plans to stagger the rollout to avoid simultaneous digging across multiple neighbourhoods and minimise traffic disruption.
We will start third phase work after completing the first two phases of concretisation,” Additional Municipal Commissioner Abhijit Bangar said, confirming the timeline.
Under the first two phases, the BMC undertook concretisation of 2,175 road stretches covering 706.55 km at a combined cost of nearly Rs 17,000 crore. Of this, work on 486.75 km has been completed, while concretisation of 96.45 km is currently underway. Work on the remaining 67.34 km is yet to begin.