Changing City: BKC-Dharavi travel to get quicker, girder launch set to start on Mithi River bridge

Reported by The Indian Express

The Mumbai civic body, the Brihanmumbai Municipal Corporation (BMC), is set to begin girder launching on the new bridge linking Bandra and Dharavi over the Mithi River. The move may improve Mithi’s flow and boost connectivity between the suburbs and South Mumbai.

The new bridge is part of the second phase of a Rs 204 crore project launched to widen the existing bridge to 10 lanes. About the project As part of the Mithi River basin widening project, the civic body plans to raze the existing and nearly 50-year-old bridge between Bandra and Dharavi to make way for a new, wider bridge.

The project secured final approvals in 2019, and the civic body began phase-wise work on the river bridge. The bridge starts near Bandra Kurla Complex's Jio World Drive road junction along the Western Express Highway and then ends near Dharavi, nearly 110 metres south of the Mithi River.

When its construction is over, the new bridge is expected to ease congestion and offer relief for commuters traveling to and from BKC, Dharavi and Mahim Causeway. The phase-wise construction of a new bridge The entire project is being executed in three phases.